Working days
Gantt chart durations count working days, not calendar days. A task that takes five working days, started on a Monday, finishes that Friday; started on a Wednesday, it finishes the next Tuesday, because the weekend in between does not count. Getting this right is the difference between a plan that matches the calendar and one that is quietly a week short.
Make your Gantt chart now, no signup required
Open the editor and type your tasks one per row, with how long each takes and what it waits for. The chart schedules itself as you type. Your work is saved automatically in your browser.
Create Your Gantt Chart FreeHow GanttCharts.app counts
- Durations are whole working days, Monday to Friday; a duration of 0 is a milestone. Type "2w" and it is read as two working weeks, 10 days
- A task whose start falls on a weekend starts on the next working day, and the editor says so
- Lags on a dependency are working days too: "4+2" waits two working days
- The Finish column shows a task's last working day; typing a finish date sets the duration
Converting from calendar time
When an estimate arrives in weeks or months, convert it before you type it: one week is 5 working days, two weeks is 10, and a month is roughly 20 to 22. Waiting that happens every day of the week, such as a delivery promised "in 14 days", is 10 working days.
Frequently asked questions
Does a Gantt chart count weekends?
Normally no. Durations are counted in working days, Monday to Friday, so weekends are skipped. A five-day task takes one calendar week.
How many working days are in a month?
About 20 to 22, depending on the month and how its weekends fall, before any public holidays.